New curbs for Birch Glen

The first stage of work on new curbs for the neighbourhood has begun with trenches dug along the south side of Andros Blvd. and on Zante Cres.  Markings and cuts have been done on one side of each of the other streets in the neighbourhood, which means that the old curbs will soon be removed and new curbs installed. Work is being done first on one side of each street; when that side is completed, work will begin on the other side.

We have been informed that the work will progress in stages:
  • curbs will be replaced first
  • boulevard sections of driveways will be done next
  • repaving of streets will be done last
Information on driveway reconstruction will follow in a separate posting.